Do you dare to say what items are included in the decoration finishing project?

2022-01-25


The finishing touch of the decoration is the last part of the decoration. If it is successfully completed, a complete home will be presented in front of you. But do you know exactly which items are included? It doesn't matter if you don't know, I will give you a detailed list below.

1. Cabinet installation

After the ceiling is finished, the cabinet can be installed on the door. If it goes well, it can be done in one day. At the same time, there are also a sink (which may not include the upper and lower water parts) and a gas stove. Before installing the cabinet, it is best to coordinate the property to pass the gas, because the gas stove needs to be tested after the installation.

  2. Wooden door installation

The production cycle of wooden doors is generally one month. Therefore, in order to make the construction period closely connected, the wooden door manufacturer should come to the door to measure the size of the door opening as soon as possible after the main body is demolished and modified. Regarding the handling of door openings, everyone needs to pay attention to one thing. If the height of the door openings in the house is inconsistent, it needs workers to handle the same height to look good.

Do you dare to say what items are included in the decoration finishing project?

3. Floor installation

The floor can be installed on the second day of the wooden door installation, and if it goes well, it is also a day's time. Floor installation needs to pay attention to the following issues: Before installing the floor, it is best to ask the manufacturer to investigate whether the ground needs to be leveled or partially leveled; and the floor where the floor is laid at home should be cleaned to ensure that the floor is dry, so do not use water during the cleaning process. .

4. Switch socket installation

Generally, the switch is turned on and off with the opposite hand, and the right hand is used instead of the left hand. Therefore, most of the switches at home are installed on the left side of the door, so that it is convenient to use the right hand to open the door after entering the door. Consistent with behavioral logic.

5. Lamp installation

Lamp colors are available in white, yellow and blue (purple). Don't use other colors, just like red and green. The former is simply a pornographic place, the latter a horror zone. After the lamp is installed, the house is lit up, saying goodbye to the dazzling glare of the 100-watt incandescent light bulb during the renovation.

6. Hardware sanitary ware installation

The upper and lower water pipe fittings, bathroom pendants, toilets, drying racks, etc. that have been bought before are all installed together. After the "big pieces" in the front are installed, the home is still very "cold". After the lamps and hardware are installed, the home is "live".

圖片名稱

zhboyen@zhboyen.cn

Contact us for any questions

圖片名稱

Live Chat

Mon-Sat: 8:00 AM - 8:00 PM Central Time

We Carry the best Outdoor Wicker Patio Furniture from the following manufacturers:

logo

Copyright© 2022 ZHUHAI BO YEN HOUSEWARE MANUFACTORY LTD. All Right Reserved.     Powered by:www.30.cn SEO TAG